TM 1-1730-231-13&P
3-25. MANIFOLD
3-25
This task covers:
A. INSPECTION
B. REMOVAL (AVIM)
C. INSTALLATION (AVIM)
INITIAL SETUP
Tools
Shop Set, AVIM, Hydraulic, NSN 4920-00-165-1454
Personnel Required
Equipment Condition
MOS 68H
Manifold disassembled
Reference Information
Equipment Condition Paras:
Appendix C, Figure 6
3-18 through 3-24
General Safety Instructions
WARNING
Be sure that all electrical power is removed from
the unit before beginning any maintenance
operation.
To avoid personnel injury, the pump must be
shut down before beginning any maintenance
operation.
NOTE
Tag all disconnected wiring and tubes to ease
reinstallation.
A.
INSPECTION
Check condition of manifold for cracks, fracture, or damage.
B.
REMOVAL (AVIM)
1.
Remove attaching hardware securing solenoid coils and lift off solenoid coils.
2.
If coils have to be removed, remove attaching hardware and wire lugs from junction box for the respective solenoids
and remove solenoid coils.
GO TO NEXT PAGE
3-30
|