STEP
38.
Remove all test equipment.
a.
Tighten nut (Figure 50, Item 4) on charge valve (Figure 50, Item 5).
b.
Close nitrogen tank valve (Figure 50, Item 1).
c.
Back off regulator valve (Figure 50, Item 2), open bleed valve (Figure 50, Item 9), and bleed hose pressure
to 0 psi.
d.
Remove adapter valve (Figure 50, Item 7) from charge valve (Figure 50, Item 5).
e.
Remove pressure measuring device (Figure 50, Item 3) from bleed valve (Figure 50, Item 9) on charging
harness.
f.
Install charge valve cap (Figure 50, Item 6) on actuator accumulator (Figure 50, Item 8).
3
1
2
9
8
5
4
5
6
7
T01368HDC
Figure 50. Actuator Accumulator Charging.
CONDITION/INDICATION
Verify problem is solved.
DECISION
YES - Problem is solved.
NO - Notify Supervisor.
END OF WORK PACKAGE